<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">8</journal-id>
      <journal-title-group>
        <journal-title>《科技研究》</journal-title>
      </journal-title-group>
      <issn>ISSN:3079-9244（原2717-5480）</issn>
      <publisher>
        <publisher-name>华文科学出版社</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.12421/ddyx3079-9244-2025440</article-id>
      <article-id pub-id-type="publisher-id">18499</article-id>
      <title-group>
        <article-title>2027 倒计时：三甲医院 EPC 项目双减、三重管控体系构建</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>于小晨 (中国新兴建设开发有限责任公司 北京市 100039)</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2025</year>
        <month>4</month>
      </pub-date>
      <issue>4</issue>
      <abstract>
        <p>在“减投资、减建筑面积”的“双减”政策约束下，三甲医院 EPC 项目面临进度、成本与医疗工艺的多重挑战。
本文以 2027 年项目交付为目标，构建了进度、成本、医疗工艺三重管控体系：进度管控通过 WBS 分解、关键路径优化
及“BIM + 物流”监控，实现全周期动态调度；成本管控依托“目标+责任”双轨预算、供应链优化及价值工程，达成精益
化成本控制；医疗工艺管控聚焦流程优化、专项工程质量闭环及多专业协同，保障空间压缩下的功能达标。
本文以某三甲医院为案例验证了体系的有效性，其通过“时空压缩” 施工、“BIM+EPC” 数字孪生等中国设计创新
技术，在投资减少约 20%、面积缩减约 10% 的情况下实现了医疗功能升级。研究为“双减” 背景下三甲医院 EPC 项目的
高质量建设提供了可复制的管理路径，彰显了中国设计在医疗工程领域的系统性解决方案能力，未来可结合 AI、区块链等
技术进一步优化管控效能，为国家医疗基建战略实施提供有力支撑。</p>